Evaluation of fitness-for-purpose
To
address the problem of fatigue failures of internal
heat exchangers in a large industrial pressure
vessel, a SixD engineer worked with an international
engineering team to develop a measurement and
analysis strategy that evaluated the
fitness-for-purpose of the current system under
operating loads. The vessel system was instrumented,
and critical load path strain responses to operating
conditions were measured. The fitness-for-purpose
evaluation showed very high levels of fatigue damage
during normal operations and a short remaining
fatigue life. After this evaluation, the client was
able to initiate a redesign process before the system failed, using
the measured loads as a baseline. The heavily
damaged system was replaced during a controlled
outage, minimizing disruption to the production
schedule.
Benefit: Instead of reacting to a catastrophic failure, the
customer was able to plan for system replacement.
Service:
High-level consulting
|